Integrated Drilling System
The IDS can be supplied to operator in 4-12 months lead time, where the lead time largely depends on level of commitment, SPS supplier selection and IDS rental pool availability.
To secure delivery, NST encourage the operator to place an early commitment for long lead items such as SPS HPWHH and forgings.
SPS suppliers which have gone through design verifications and qualification for their HPWHH with integrated compact flange may typically require 6-9 months lead time
SPS suppliers which require internal engineering and design qualification will typically add 3 months lead time and be able to supply its HPWHH with compact flange design in 9-12 months.
If there is availability in the IDS and HPWHH rental pool, lead time and delivery will be less than 4 months.
Typically manufacturing time for the IDS, CAN and HPWHH is 6-12 months.
New Subsea Technology AS
c/o Sigbjørn Madsen
Raunen 19
4158 BRU
Phone: +47 901 67 029
Mail: post(at)newsubseatechnology.com
Copyright © 2018 New Subsea Technology. All Rights Reserved.
Privacy Policy (Coming)